Thursday, April 9, 2015

Spring Weather & 1st Mow

As expected the winter weather had little effect on the new bentgrass planted on greens, tees and fairways as part of the Renovation Plan.  As the snow melted Grounds went back to work preparing to open the golf course in early June.  TDI is set to return in mid-April to finish up cart path work and some minor sodding.  Follow along on Twitter and the Blog as we prepare to open! 


Snow melt in late March revealed no winter damage here on the 17th green or anywhere else on the golf course.


The 6th fairway after the spring thaw is in great condition.  The BBB and ProAngle sand stayed in place just as we left off in the fall.




The 1st mow on greens took place on March 20th (above).  The third mow on April 8th (below) shows some very nice green up despite the cold temperatures.



The short game area and 18th fairway were both seeded late in the fall and covered over the winter.  We removed covers on April 7th and are very pleased with the results.



A few of the shaded tees required sodding in order to be ready in time for opening.  Our crew (above) works from plywood to sod the 13th tee.


Bail areas behind 4 of the greens were also sodded early this month to 007 bentgrass.  The finished product looks fantastic! 




Friday, January 23, 2015

Winter Tree Work

The cold weather and frozen ground has allowed us to drive our  heavy equipment on the golf course and continue our Ash Tree removal and replacement program.  Several Ash trees we have removed show extensive damage from the Emerald Ash Borer.  Our goal is to remove all Ash Trees over the next several winters and phase in a diversity of new trees planted in strategic locations.  The first of these plantings will take place this spring in conjunction with the Renovation Plan.



This is the first evidence I've seen of cold weather damage.  The recent cold snap caused this tree to split.  Unfortunately we'll have to remove this tree for safety reasons.




Tunneling of the Emerald Ash Borer is evident in the photos below.









video

Wednesday, November 5, 2014

Before & After

A quick look at some before and after renovation pictures.  Click on any picture to enlarge and view as a slide show.   More to come... 



The 2nd greens looking towards the 3rd blue tee.  Pure 007 Bentgrass vs the mottled Poa & Bent.  Consistent surrounds that flow to the next tee. 








The 12th green and bunker complex.  Nice movement against the green, bunker pushed closer and clean sod on the surrounds.  








11 Tee - Level and firm








Approach bunker on the 2nd hole.  Notice how the greenside bunkers are much more visible after renovation.








8th hole from the back tee.








15th tee - Square, level and firm








Greens - Bent/Poa vs 007 Bent




Friday, October 24, 2014

Renovation Update

A couple of heavy rain events slowed production of bunker shaping for a few days however we remain on schedule for substantial completion by mid November.  Bunker work continues with holes 8 and 9 the only remaining holes to shape.  Better Billy Bunker, sand and sod are following closely behind having progressed through 10, 4 and 15 near the halfway house.  Greens tees and fairways are filling in nicely and have all been mowed except for the 18th fairway.


Crisp fall days are perfect for completing the project.  Next week looks to be more of the same.


Bunker shaping on 15 green.



Despite the heavy rain events the BBB and ProAngle sand are performing as advertised.  Not a single washout!


Poa annua roots (right) from the PPG are no match for 007 Bentgrass (left) from the 13th green.


Squirrels are not helping the cause here!


We've utilized covers to help keep the soil temperatures warm and aide growth as well as keep the squirrels off.

Tuesday, September 30, 2014

Renovation Weeks VIII & IX

Perfect weather over the last two weeks helped us finish off the seeding off all bentgrass areas, and gave us a great start on bunker work.  A glimpse of the the bunker renovation process can be found below.


After old bunker sand is removed, rough shaping of bunkers begins with a bulldozer.  


Further shaping and edging is performed by hand and with smaller equipment.


Final shaping is approved by our architect taking into account many factors including visibility from the tee or fairway.


Drainage lines are trenched and pipe is installed.


Gravel is then placed in the floor of the bunker.


Better Billy Bunker polymer is sprayed over the gravel layer locking the gravel in place.



Bluegrass sod is installed around the perimeters before placement of the ProAngle bunker sand.






Monday, September 15, 2014

Renovation Weeks VI & VII

On and off rain the past two weeks slowed some of the earth moving and grading, but was just what the doctor ordered for the new seedlings.  Thankfully all of our greens are firmly established, and we are past the point where heavy rain will cause washouts and setbacks.  So far all aspects of the project remain on or slightly ahead of schedule.  A glimpse of the past few weeks can be found below.



Most greens have been mowed 6-7 times at this point at about 1/4" height of cut.  The 15th green is pictured above receiving a fresh cut and the 7th green is below.



Most fairways have been mowed 2-3 times at this point and are filling in nicely.  Four fairways are receiving some final grading and prep work before seeding later this week.  The 8th fairway is pictured above and below.



All tees have been seeded at this point.  Seeding of the 13th tee is pictured above.


Bentgrass germination on a fairway 5 days after seeding.


Fairway drainage repair and upgrades are pictured above and below.  Most of this work is being performed by RCC staff.



All tees received a "ring" of bluegrass before seeding.  Our contractor has installed 12 semi loads of sod to date.


Grading of the fairway expansion on the 5th hole is underway, and the new lake is complete!